Mismanaged from the opening faceoff, The Gretzky Centre Project was put back on track by the WGSC Steering Committee. The committee was first chaired by former councillor Greg Martin. I became chair at the start of this term of council and was ably assisted by Councillors Debi Dignan-Rumble and Larry Kings.
Though the committee took millions of dollars in savings from the budget, the damage had already been done - thanks to poor initial estimates, lousy oversight and inexperience. The project finished significantly over budget.
That was the bad news.

The good news is - we have a facility second to none. Not only a premiere hockey facility, but a multi sport facility and neighbourhood hub with a walking / running track and restaurant. I'm very proud of our accomplishment.